All the water services stubs have been installed to the right-of-way line, which means water service is available for all residents. As of July 2, fifteen (15) houses (21%) have connected to the municipal water system.

Quotation forms have been received for 64 houses (90% of the neighborhood). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so soon. The neighborhood is approximately halfway through the 60-day requirement for getting water services connected.

Bultsma Excavating has an underground sprinkling contractor scheduled to complete the sprinkling repairs next week. Bultsma Excavating also has concrete crews scheduled to finish up the remaining concrete work next week.

Final lawn restoration and project cleanup is scheduled to start end of next week after sprinkler repairs and final driveway/sidewalk restoration are completed.

Have a safe and enjoyable Fourth of July weekend!

 

What to Expect Next Week (July 6 – 10)

 

Projected Timeline