DeSal focused most of their effort this week on water main testing and water service installation. Water services have been installed up to around Imperial Pine Drive. There are still a few water services that need to be bored under the road south of Imperial Pine Drive. Residents will receive a letter when their water service is ready for connection.

DeSal and the Plainfield Water Department continued to pressure test and disinfect sections of water main as they were completed so that water service installation can continue.

Water service Quotation Forms have been received for about 23% of the houses along House Street. If residents have not yet talked to a contractor about installing their private water service, they should make contact as soon as possible.

Have a safe and enjoyable Fourth of July weekend!

 

What to Expect Next Week (July 6 – 10)

DeSal will continue installing water main along the north side of House Street, pressure testing and disinfecting the water main, and installing water service stubs. DeSal plans to be done with water main installation by the end of next week which will allow them to focus on water service installation.

 

Projected Timeline