Work Completed this Week

  • Jackson-Merkey Contractors, Inc. completed the installation of the sanitary sewer in the SW-NE Alley from Fourth Street to the intersection with the NW-SE Alley.
  • Jackson-Merkey Contractors, Inc. completed the installation of the sanitary sewer in the NW-SE Alley from the intersection with the SW-NE Alley towards Merrill Avenue.
  • Martin J Concrete, Inc. constructed curb and gutter, sidewalk and drive approaches on Fifth Street.

 

Anticipated Work Next Week

  • Jackson Merkey plans to continue the sanitary sewer in the NW-SE Alley from the intersection of the SW-NE Alley towards Mason Avenue.
  • Jackson-Merkey Contractors, Inc. plans to fine grade the aggregate base on Fifth Street and anticipates paving on Wednesday or Thursday of next week.
  • Jackson-Merkey Contractors, Inc. plans to begin restoration and placement of turf establishment items.
  • Jackson-Merkey Contractors, Inc. plans to continue grading and placement of aggregate surface course in the SW-NE Alley between Fifth Street and Fourth Street.

 

Current Road Closures

  • Fifth Street from Merrill Avenue to Mason Avenue.