Progress Report:
This week Miller Bridge completed the work on the new expansion joints in the bridge, including setting the new steal joint devices and repouring the concrete deck around it.
At the abutments, the helical piles are driven and tested, therefore the wall subcontractor built the forms and is now preparing to pour the footing for the block retaining walls at the ends of the bridge.
Upcoming Work:
Miller bridge anticipates that they will begin forming and installing the forms for the concrete and steel reinforcement for the H piles in the bayou.
In addition, the contractors will pour the footings and start building the block retaining walls.