Work to Date

  • Watermain has been placed, tested, tied-in and crews have stubbed water services to the right-of way line in the following locations.
    • Burger between Goodwood and the west end of the job limits (6950 Burger).
    • Cimarron between Goodwood and Tuscany.
    • Tripoli between Burger and Tuscany and on Tripoli Court.
    • Tuscany between Burger and the west end of the job limits.
  • Watermain has been placed along Tanglewood between Burger and Thornapple River Drive.
    • Pressure testing and chlorination is complete.
    • Services are ongoing.
  • Watermain has been placed along Tricklewood between Tanglewood and Brookhills Ct and Brookhills Ct east of Tricklewood.
    • Pressure testing and chlorination is complete.
    • Services are ongoing.
  • Contractor has completed the installation of the new storm sewer on Burger between Tanglewood and the bayou and between Tuscany and 6920 Burger.
  • Restorative efforts are continuing, and damaged irrigation systems are being repaired.

 

Work Upcoming

  • Crews will continue to work on water service installation on Tanglewood, Tricklewood and Brookhills Ct.
  • Watermain installation on Tricklewood is expected to begin in the next few weeks, starting at the Tanglewood intersection moving south towards Tricklewood Ct.
  • Crews will continue restorative efforts in completed areas.

 

General Notes

  • Residents should be aware that after your yard has been dug it may be up to a month before we are able to complete the work and repair irrigation systems.
  • The contractor will be responsible for establishing grass growth.  For best results residents are encouraged to regularly water the hydroseed and mow down any weeds that do come in.