Progress Report:
- Maple Street: The water main tie-in at Main Street has been completed. All remaining water services along Maple Street are planned to be completed by the end of this week. Concrete work for sidewalk, curbs, and driveways is planned to begin next week.
- Lincoln Street: All storm sewer installation including laterals and structures on Lincoln Street has been completed between Maple and Courtland Streets. Water main construction to the South of Maple is planned to be completed by the end of this week. Sanitary sewer construction, including laterals, to the South of Maple is planned to begin following water main construction.