Gravity Sewer Construction

Approximately 1,600’ of 21” gravity sewer has been constructed in the field between the Hampton Inn and truck wash. Installation of 21”, 15”, and 8” gravity sewer towards the Pilot Lift Station will continue through the next several weeks. Due to difficult soil and groundwater conditions, minor adjustments to the proposed sanitary sewer alignment and profile near the Super 8 Hotel have been made. Coordination with MDOT for the highway crossing portion of the project is ongoing. Work on the west side of the highway is anticipated to be complete in late July or early August.