**Paving of Exchange Street and Division Street is scheduled for Saturday June 22, 2019. **

Work Completed This Week:

West Michigan Dirt Works completed water main construction on Cutler Street.
West Michigan Dirt Works worked on installing curb and gutter and grading the road in preparation of paving.
Anticipated Work Next Week

West Michigan Dirtworks raising manhole covers, concrete flat work and paving the top course of Exchange Street and Division Street.
West Michigan Dirtworks complete water services on Cutler Street
West Michigan Dirtworks complete restoration of Beechtree and the parking lot at City Autobody.
Comments

During paving access for driveways will be intermittently blocked. The Contract will work to notify residents prior to paving.