All lead water service work on Pinehurst, Waverly, and Wilmette will be completed by Friday, June 21. Base paving on the north end of Pinehurst is scheduled for the week of June 24.

Water main in Campbell should be installed from Pinehurst to Commonwealth by the end of next week. Once that section passes the required tests, water service work will immediately follow.

The lawn restoration schedule is being reviewed given the current heat wave and will begin when there is a reasonable expectation that new grass can be seeded without significant risk of being killed by the heat.

Once water main is installed in Campbell, the crews will move to Dartmouth and Clarendon. The work crews thank everyone for their understanding and patience as the construction progresses.