The I-94 BL was reopened to traffic on 6/16. Access to Lake Street off the BL is still closed. Curb/gutter placement from Schuster to BL is planned for the week of the 26th. Shortly after that the road will be paved and opened to traffic.
Construction progress is ahead of schedule as work in Phase C has begun this week with Lake Street road removals between Lamont and Bronson Ave. Unground work on Phase C is planned to start the week of the 26th.
The total project completion date has been moved up from Dec. 1st to Nov. 10th due to the amount of work already completed. Road building on the East side of the BL will move along much quicker than the West side due to favorable existing soil conditions. Expect to see a more aggressive schedule going forward.
Upcoming Construction Milestones:
- Paving of the road from BL to Lamont is tentatively scheduled for mid-July.
- Paving of the road from Lamont to Roy Ave is tentatively scheduled for mid-Aug.
- Paving of the road from Roy Ave to Olmstead is tentatively scheduled for mid to late Oct.