This update comes early due to an upcoming road closure. Work this week has progressed nicely. Hallack Contracting will be closing down the Loomis Street and James Street (U.S. 10) intersection for the next two weeks starting Monday morning. This will be a complete road closure at Loomis Street requiring a detour route. The posted detour route will be Rath Avenue from Filer Street to Ludington Avenue. Access to businesses along James will be maintained from Ludington Avenue and Filer Street.

 

Work Completed This Week

 

Anticipated Work Next Week