Curb and gutter installed and asphalt placed from West project limits to Schuster Ave. Access to Schuster Ave will now be from the West off Shakespeare. Access to Lake Street West of the BL has been closed for construction. Lake Street is now closed in both directions (E/W) from the I-94 BL.
Sanitary sewer install completed from BL to Lamont Ave. Completed water service connections to the new water main from the BL to Lamont Ave. Underground utility work has begun between Schuster and the BL.
The I-94 BL will be closing to traffic from King Hwy to Olmstead starting on June 12th. Water main install across the BL is anticipated to take a week. Once testing is complete and the road rebuilt the BL will be opened back up to traffic no later then the 22nd.