The general contractor has notified the City/Township of their intention to begin work on April 10, 2023.  Residents should be aware that construction equipment and materials may begin arriving on-site when frost laws have been lifted, which is expected to be during the week of March 27th.

Construction is slated to start at the Burger Dr/Goodwood Dr intersection and work NW toward the bayou crossing. A general schedule is shown below, but residents should be aware that weather, site conditions, and crew productivity can often affect schedules on projects such as this.

 

Burger Drive between bayou and Goodwood:

 

Burger Drive bayou crossing:

 

Burger Drive between bayou and the west project limit:

 

Cimarron between Tuscany and Burger:

 

Tripoli Drive between Tuscany and Burger:

 

Tuscany Drive between Burger and the cul-de-sac:

 

Tanglewood Drive between Burger and Thornapple River Drive:

 

Tricklewood between Brookhill Ct and 3564 Tricklewood:

 

Tricklewood Ct. between Tricklewood and cul-de-sac:

 

Brookhills Ct between Tricklewood and cul-de-sac:

 

Water service placement in areas located adjacent to existing water main is ongoing. Plumbing companies are also quoting connections for residents in Phase I. If you have not done so already, please reach out to one or both of the two pre-qualified plumbing companies about connecting to municipal water.

If residents have specific companies that they use for irrigation, landscaping, or repairs to any underground fencing, they are encouraged to send the name and contact information to goodwoodwater@gmail.com.