Progress Report: Dykema Excavators is making good progress installing the new water main along Northland Drive. Traffic along Northland Drive will continue to be flagged until the water main work along Northland Drive is complete. We appreciate your patience as this work continues over the next two weeks.

Upcoming Work: The bore & jack under M-44 is scheduled to be completed next week. Dykema Excavators will continue to install water main along Northland Drive up to Kuttshill Drive next week.