Progress Report:  CL Trucking & Excavating has completed the water main installation along Kittery Drive with the exception of the tie-ins at Westgate Drive and Westshire Drive. CL will begin water main installation on Bowdoin Pines Court on Friday.

Upcoming Work:  CL will complete the water main installation on Bowdoin Pines Court next week and then move to Bingham Court after that. CL will begin pressure testing and disinfecting sections of the new water main with the Plainfield Water Department in preparation for water services to be switched over in early April.