Montgomery Excavating has indicated that they anticipate starting construction the second week of June. Water main and water service construction is anticipated to last for approximately three weeks. Driveway and lawn restoration will take place after the water main work is completed and will last one to two weeks.
The water main will be installed on the north and west side of Warwick Glen Drive. Any landscaping within the public road right-of-way will be removed as necessary for water main construction and will not be replaced as part of the project. If you would like to save any landscaping, it is recommended that it be moved prior to construction. For reference, the edge of the public road right-of-way is approximately 33-feet from the center of the road.
Please contact any project representative if you have questions or concerns.