Progress Report:

  • This week Miller Bridge continued work on expansion joint replacement on the Green Street Bridge, including competing the sand blasting of the existing beams and installing new pins and hangers at both joints.
  • They also continued working on the pathway, east from 144th Avenue. Work has included brush removal, topsoil removal and stockpile, and placing sand, and gravel.
Upcoming Work:
  • Next week Miller Bridge will begin work on installing new expansion joints on the bridge. They are also planning to begin installing the new H-Piles in the Bayou for bridge expansion.
  • Work will also continue work on pathway towards the Green Street Bridge.