I hope this update continues to find everyone in good health and continued safety.  I [Derek Gajdos] apologize on behalf of all the project team members for all of the delays this project has experienced. While we did see the south bound top course paved on Tuesday, we witnessed two more delays this week getting the final top course of asphalt laid. The paving subcontractor, Michigan Paving Materials, had a plant failure on Wednesday and weather is preventing paving today (Thursday, May 28).  They  are prepared for paving the final northbound top course on Friday, May 29.

 