Work to Date
- Watermain has been placed along Burger between Goodwood and Tuscany.
- The main has passed all testing and has been tied into the existing system.
- Crew have continued stubbing water services out to the right of way line.
- Watermain has been placed along Tripoli between Burger and Tuscany and on Tripoli Court.
- The main has passed all testing and has been tied into the existing system.
- Crew have begun stubbing water services out to the right of way line.
- Watermain has been placed along Cimarron between Goodwood and Tuscany.
- The water main is being pressure tested and chlorinated.
- Watermain installation through the bayou on Burger between Tuscany and Tanglewood began and is nearing completion.
Work Upcoming
- The Contractor and the City of Grand Rapids will complete the pressure testing and chlorination of the new watermain on Cimarron.
- Once completed, crews will begin stubbing out new water services.
- The Contractor will continue stubbing water services on Tripoli and Tripoli Court.
- The Contractor anticipates that crews will replace storm sewer on Burger between Tanglewood and Goodwood.
- Asphalt paving crews are scheduled to be on site by the end of the month to replace sections of road that were removed, and will begin replacement of drive approaches.
- This is dependent on weather condition suitable for paving.
- Concrete driveway replacement will occur at a later date once an appropriate amount has been reached for the concrete crews to have a full day’s work.
- Contractor will also replace the guardrail that was removed by the Burger bayou in the coming weeks.
- Watermain installation on Tuscany is also slated to begin.
- Crews will continue restorative efforts in completed areas.
General Notes
- The lane reduction/daytime closures on Burger between Tuscany and Tanglewood will remain in place until the storm sewer can be installed, the guardrail can be replaced, and the road reconstruction completed. It is anticipated that this will be completed by the end of the month.