Last Week
Crews from Dykema Excavators continued to work on the large block retaining walls along 9 Mile Road. There are a total of four of these large block walls, and the last and largest of these retaining walls is currently being built.
Next Week
The crews expect to be nearly finished with the retaining walls. Once complete, they will move on to preparing the gravel base for asphalt. They have also been preparing the sidewalk ramps and boardwalk abutments for the concrete that will arrive next week.