This week Miller Bridge continued work on maintenance items on the Stearns Bayou bridge, including expansion joint replacement and metalizing the existing beams at the joints. In addition, starting at 144th Avenue and moving east, crews continued work on the pathway, stripping topsoil and placing sand and gravel base.
Next week Miller anticipates continuing work on the bridge joint replacement, starting with placing forms and pouring new concrete for the joint. Work on the pathway will continue as well. Miller plans to remove driveways as necessary and replace the driveways with temporary gravel for access.