This week, despite the cold weather, crews were able to make great progress on pathway and boardwalk construction!

The first layer of asphalt was completed on a majority of the pathway and they were also able to pave the top layer along Whitneyville. Crews worked hard in the chilly temperatures to get the remainder of the grading work completed, while the boardwalk crews continued install piles and framing on the boardwalks.

Next week, the crews will continue the restoration efforts and begin working on site clean-up. There is still a second layer of asphalt to pave on 66th and McCords. They hope to have the pavers back out to complete that work next week. Crews will also begin the earthwork preparation process for the concrete work, which will take place by the end of next week if the weather permits.