This week, pathway progress continued on the north end of the Jericho Avenue project. Crews continued to remove existing material and install the gravel sub grade. They will install concrete driveways and curbs yet this week.
Next week, they hope to finish the remaining concrete work and, if the weather permits, they will schedule the paving on the remaining sections of pathway to the bridge.
On Airway Street, the crews plan to be back out at the beginning of the week to begin the restoration work in front of the KIA property. They also anticipate that they will have the paving contractor out by the end of the week to finish paving on Airway Street.