Work completed/in progress:

  • Southbound US-31 on-ramp restored.
  • Completed force main installation in Colby Street and Peterson Road.
  • Force main installation completed near Oakhurst Cemetery.
  • Completed force main installation east of Whitehall Road to PS Whitehall, including sliplining the existing 16″ ductile iron force main.
  • Restoring Colby Street
  • Acceptance testing of force main east of Whitehall Road.

 

Anticipated work activities for the coming week:

  • Finish Colby Street road building and pave.
  • Hydrostatic test 22″ force main west of Whitehall Road.
  • Continue pipelaying through easement toward sewage pump station near the ball fields.