Progress Report

This week:
  • Deans worked on installing the water on the private gravel drive south of Rogue Hill Court.
  • Dean’s will complete the final water main tie-in on Van Dam Drive pending passing disinfection test results.
Next week:
  • Dean’s will install water services on Van Dam Drive.
  • Dean’s will pressure test and disinfect the new main on the gravel drive south of Rogue Hill Court. Once the tests have all passed, Dean’s will install water services on this new main.

 

What to Expect

November
  • Water main construction along private gravel drive south of Rogue Hill Court
  • Water service construction along Van Dam Drive and private gravel drive south of Rogue Hill Court
  • Project clean up
Spring of 2022
  • Water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive.

 

Important Information

Only those houses along Packer Drive (including the two gravel drive easements south of Rogue Hill Court) and Van Dam Drive will receive a water service as part of the 2021 construction and will be required to connect to it this year. Water main and services on Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive will be constructed next year with connection required for these houses in the spring of 2022.

 

Project Timeline

November
  • Water service installation along Van Dam Drive
  • Water main and water service construction along private drive easement just south of Rogue Hill Court.
April 2022
  • Water main construction along Packer Woods Drive
May 2022
  • Water main construction along Rogue Hollow Drive and Rogue Hill Drive