Progress Report

Private water service installation continued throughout the project area. If you have not already contacted a prequalified general contractor to install your water service, you must do so as soon as possible to ensure that you can meet the 60-day connection requirement.

As of November 2, twenty-three (23) houses – 33% of the project – have connected to the municipal water system. See status map above for reference.

If you have any questions about the process for getting your water service installed into your house, please contact Jeremy Kamp (contact info on the left).

 

What to Expect

November
  • Private water service installation