Macatawa River HDD: Reaming progress continues. Gabe’s completed the 24-inch reaming pass and began the 36-inch ream this past week (see below pictures). Once this reamer is complete, the last 45-inch reamer will be bored, followed by the HDPE pipe pull back.
Tree Removal: K&R began the tree/brush removal process in preparation for force main pipe installation this coming winter (’24) and spring (’25), mainly along the HBPW electric corridor and James Street (up to Beeline Road).
Material Delivery: Pipe and material delivery continues, as stockpiles can be seen along James Street & River Hills Drive.