Progress Report:

This week Miller Bridge focused on the removal of part of the existing bridge deck and the brush block sidewalk on the north side of the bridge. Other crews continued work on the pathway to the east, clearing, grading, placing gravel, and working on restoration on sections already paved.

Upcoming Work:

Next week they will continue removing the crushed deck and sidewalk, and then forming for the new deck. They anticipate pouring the back walls at the abutments this weekend. In addition to the clearing and grading for the bike path, they anticipate paving the top course on the completed stretch on Wednesday, and then paving the base course on sections they have ready to the east.