Progress Update:

Construction on the Conrail Lift Station and Interceptor project has started! Dewatering and clearing of the site near the lift station has begun in preparation for the wet well installation.

 

Up Next:

Installation of the forcemain from Pipestone Road to the unnamed private road east of Ox Creek is scheduled for late next week. This pipe will be installed by horizontal directional drilling, thereby avoiding clearing and disturbance of the wooded wetlands and creek. Installation of the lift station wet well is also scheduled to begin next week.

 

Pipestone Road Traffic Closure:

The first of two Pipestone Road traffic closures is scheduled to begin October 17. Pipestone Road will be closed to through traffic from Napier Ave to Mall Drive, with a detour following Napier Ave, Plaza Drive, and Mall Drive, as illustrated on the map above. Pipestone Road will be fully closed at the work area located near the Aldi grocery store. Residences and businesses north of the work area, including Aldi, will remain accessible from the north. Businesses south of Aldi will remain accessible from the south. This traffic closure is scheduled from October 17 through November 3.