This Week

Construction crews have completed all new water service installations. All sanitary sewer has been installed on Sunset Street and John Street, with sanitary sewer installation continuing on Greenfield Street. Storm sewer work on Sunset Street has started and will continue until complete.

The contractor has begun restoration efforts on Center Street with concrete curb being poured and asphalt road restoration soon to follow.

Concrete Curb, sidewalk, and driveways will start to be poured on Sunset Street, Greenfield Street, and Oriole Street once a majority of all underground pipe work is completed in the upcoming weeks. Crews will be communicating with residents in the upcoming weeks about access limitations during the concrete pour.