Progress Report

Final paving in the Bonneville Drive area is scheduled for Saturday, September 25.

 
This week:
  • General project cleanup was completed in preparation for final paving.
  • The rain has delayed the final top course paving in the Bonneville Drive Area. Black Gold is scheduled to have two crews on site Saturday, September 25, to pave Bonanza Drive, Bonneville Drive, court streets, and the remaining driveways.
 
Next week:
  • H&K Landscaping, Schipper’s lawn restoration subcontractor, will be on site to begin final lawn restoration.

 

What to Expect

September – October
  • Water Service conversions along Plainfield Avenue
  • Final paving, restoration, and project clean up