Progress Report
This week:
- Wyoming pressure tested and disinfected the new water main on Pixley Avenue.
- Wyoming Excavators completed two water main tie-ins on Pixley at Belmont Avenue and Van Dam Drive. All of the new water main is now installed!
- Wyoming Excavators completed water service installations on Wildwood Creek Drive and began installing water services on Pixley Avenue.
- Wyoming Excavators began grading the road on Wildwood Creek Drive in preparation for paving in early October.
- Wyoming Excavators completed storm sewer work along Van Dam Drive.
Next week:
- Wyoming Excavators will complete water service installation on Pixley Avenue.
- Wyoming Excavators will continue grading the road on Wildwood Creek Drive, paving is tentatively scheduled for 10/11.
What to Expect/Project Timeline
October
- Wildwood Creek Drive road reconstruction.
- Water service construction along Pixley Avenue.
- Road and driveway restoration.
Estimated project completion date: October 23, 2021