Progress Report

This week:
  • Wyoming pressure tested and disinfected the new water main on Pixley Avenue.
  • Wyoming Excavators completed two water main tie-ins on Pixley at Belmont Avenue and Van Dam Drive. All of the new water main is now installed!
  • Wyoming Excavators completed water service installations on Wildwood Creek Drive and began installing water services on Pixley Avenue.
  • Wyoming Excavators began grading the road on Wildwood Creek Drive in preparation for paving in early October.
  • Wyoming Excavators completed storm sewer work along Van Dam Drive.
Next week:
  • Wyoming Excavators will complete water service installation on Pixley Avenue.
  • Wyoming Excavators will continue grading the road on Wildwood Creek Drive, paving is tentatively scheduled for 10/11.

 

What to Expect/Project Timeline

October
  • Wildwood Creek Drive road reconstruction.
  • Water service construction along Pixley Avenue.
  • Road and driveway restoration.

Estimated project completion date: October 23, 2021