Progress Report
This week:
- Final paving in the Bonneville Drive area was completed last week Saturday.
- Schippers had an irrigation contractor on site working on repairing damaged irrigation systems.
- Schippers had their landscaper, H&K Landscaping, on site this week to work on final lawn restoration in the Bonneville Drive area.
Next week:
- Final project cleanup
- Water service conversions along Plainfield Avenue
What to Expect/Project Timeline
October
- Water Service conversions along Plainfield Avenue
- Final restoration and project clean up