Progress Report

This week:
  • Final paving in the Bonneville Drive area was completed last week Saturday.
  • Schippers had an irrigation contractor on site working on repairing damaged irrigation systems.
  • Schippers had their landscaper, H&K Landscaping, on site this week to work on final lawn restoration in the Bonneville Drive area.
Next week:
  • Final project cleanup
  • Water service conversions along Plainfield Avenue

 

What to Expect/Project Timeline

October
  • Water Service conversions along Plainfield Avenue
  • Final restoration and project clean up