**72nd Avenue between Cleveland Street and State Road will be closed starting March 31. The anticipated closure will last approximately 1 month.**
Work completed/in progress:
- Installed approximately 1,100′ of force main installed along Railroad corridor up to 72nd Avenue.
- Preparing site west of 72nd Avenue for pipeline installation.
- Flowable filled the casing beneath the former Railroad bed.
- Continued fusing lengths of HDPE pipeline.
Anticipated work activities for the coming week:
- Continue fusing lengths of HDPE pipeline.
- Resume pipe laying on north side of Railroad corridor toward 72nd Avenue.