Progress Report: Construction on the Nickerson Ave and Nickerson Ct watermain has begun! Approximately 800’ of 12” watermain has been constructed on Nickerson Ct and Nickerson Ave. Eastbound Nickerson Ave is closed to traffic, with a detour on M-139, Fairplain Drive, Plaza Drive, and Nickerson Court. Traffic on westbound Nickerson Ave continues to be maintained.

Upcoming Work: The watermain that has been installed will be pressure tested and chlorinated this week. Once the watermain has been pressure tested and disinfected, water service installation to property lines will begin. Construction of 12” watermain towards the west end of project will also continue through the end of the week.