Progress Report:

The Spring 2025 update video can be seen below, showcasing the work completed over this past winter and early spring. This includes HBPW electric corridor and James Street force main installation, CSX railroad bore & jack (42-inch casing installation), and pump station site preparation.

Pump station progress continues as the station’s wet well walls are being constructed this week. The wet well is the holding tank for the wastewater that is received from the gravity system upstream, prior to being pumped downstream to the treatment plant.

Force Main Progress:

The bore & jack has now been completed under the CSX railroad. The HDPE force main is now installed within the 42″ diameter steel casing. K&R this week is working on the force main installation along River Hills Drive.

Upcoming Work:

Pump station wet well construction will continue, along with the Lakewood Blvd bore & jack and open cut force main installation along River Hills Drive.