Progress Report: All of the water main on Nickerson Ct and Nickerson Ave, with the exception of the tie in point on the west end of Nickerson Avenue, has been installed. Half of the watermain has been pressure tested and disinfected.
Upcoming Work: Water service installation will begin on the portion of water main that has been pressure tested and disinfected. The other portion of water main will be pressure tested and disinfected this week.