It’s been another week of progress along Kinney Avenue.  Here’s what was done and what’s planned to come:

Work Completed Last Week

  • Roadway subbase and underdrain continued to be installed on the GVSU Private Drive
  • Storm sewer mainline was installed up to Hampton Lane and along the GVSU Private Drive near Kinney Avenue
  • Rough grading for the east sidewalk along Kinney Avenue has begun
  • DTE abandoned a section of gas main in conflict with the storm sewer just north of the GVSU Private Drive to allow for storm sewer installation this week

Anticipated Work This Week

  • Brenner will install mainline storm sewer in the section near GVSU where the gas main was abandoned
  • A road crew will arrive to begin installing subbase, underdrain, and aggregate base along the northbound lane of Kinney Avenue between the GVSU Private Drive and Hampton Lane.
  • The southbound lane will may also be milled within this area by the end of the week
  • Kent Power may begin installing gas services along Kinney Avenue