Following last week over 90% of the underground work for phase 1 is completed. Bulk of the work moving forward will consist of reconstructing the road.

 

Work completed:

  • Water Services for Phase 1 are complete.
  • Water main has been connected to the existing system at all points of connection.
  • Storm sewer was worked on and is nearly complete.

 

Anticipated work this week:

  • Complete storm sewer for the first phase.
  • Finalize abandonment of old utilities.
  • Start grading for the road and finalize sidewalk removals.