Work this week consisted of grading the subgrade, placing aggregate, and preparing for concrete. 

Work completed:

  • Graded subgrade for Phase 1.
  • Spread Phase 1 aggregate.
  • Completed a water main connection to Copeyon Park
 

Anticipated work next week:

  • No work is anticipated next week due to concrete scheduling.
  • Concrete is scheduled to begin September 6.