The focus this past week was on mobilization and milling for Phase I on Griswold Street. The focus this week will be on placing sanitary sewer mainline.
Work Completed Last Week
- The Contractor mobilized and stored materials on the north end of the project limits near the Griswold Street lift station.
- The Contractor began milling asphalt for Phase I.
Anticipated Work This Week
- The Contractor will begin placing sanitary sewer mainline and sanitary sewer manholes for Phase I.