Progress Update
Approximately 2,150 feet of sanitary sewer and 3,000 feet of watermain have been installed to date, as shown on the map above. Watermain installation along Euclid Ave from Territorial Road to Highland Ave has been completed.
Up Next
Watermain installation is planned to continue through the end of the week along Highland Ave from Euclid Ave to John McCoy Drive. Pressure testing and chlorination of the watermain from the green space near the I-94 Business Loop to John McCoy Drive is anticipated to occur next week.