Progress Update

Approximately 2,150 feet of sanitary sewer and 3,750 feet of watermain have been installed to date, as shown on the map above. All watermain installation is now complete, except final connections which will be made after pressure testing and disinfection.

 

Up Next

Pressure testing of the watermain from the green space near the I-94 Business Loop to John McCoy Drive is planned for this week. Disinfection is anticipated to occur the first week of January.