The construction season has come to an end on the two pathway projects in Plainfield Township.
On Jericho Avenue, Al’s Excavating and their subcontractors have completed both layers of asphalt along the pathway from Kroes to Peter Creek Drive. They will be working first thing this spring to install the storm sewer on the north side of the Rogue River Bridge and to make the pathway connection to the White Pine Trail. This work, along with sign installation and permanent pavement markings, is set to resume as soon as favorable weather permits this spring. Temporary safety measures are in place for the winter to ensure pedestrian safety and slope stability until weather permits and crews can return to finalize the construction work. We appreciate your patience with this process and hope you are already enjoying the completed sections of trail! This construction update page will remain open and will be updated with further information in the coming months.
On Airway Street, Al’s Excavating has a small amount of paving as well as sign installation and pavement markings to complete. This work will be completed in the spring along with any punch list restoration and clean up activities. We thank you for your patience with these processes and look forward to seeing you out there enjoying the trail!