This Week

Work started on the abutments for the bridge from Logan’s Landing to Medalie Park. Test piles were sunk and approved. Crews continued working on the boardwalk decking and piles across the lake. In addition, the at-grade stairs near the fishing/kayak deck were completed this week.

 

Next Week

Work will continue on the bridge abutments. Elmer’s anticipates that the abutments for this bridge should be complete next week. They will start on the next set of bridge abutments for the bridge from Medalie Park to the trail on the east side of the river. The two prefabricated bridges (90 feet long and 140 feet long) are on the way. The plan at this point is to set the bridges in place right after the holidays! 

Work will also continue on the boardwalk, which is coming together quickly.