The backwash pipe and conduit were directionally drilled. The sanitary manhole was installed and connected to backwash pipe.

Upcoming Schedule:

  • Construction of the outlet will continue, weather permitting.
  • The sump will be installed in the filter building.
  • Underground piping at the filter building has begun to be fused and will be installed.
  • Planning to sink the Crooked Pump Station wet well in the next few weeks.