The backwash pipe and conduit were directionally drilled. The sanitary manhole was installed and connected to backwash pipe.
Upcoming Schedule:
- Construction of the outlet will continue, weather permitting.
- The sump will be installed in the filter building.
- Underground piping at the filter building has begun to be fused and will be installed.
- Planning to sink the Crooked Pump Station wet well in the next few weeks.