The Napier and Colfax intersection is now open to traffic once again!  The concrete base course pavement successfully passed strength testing on Monday morning. The asphalt surface was paved Monday afternoon and the intersection in now open for traffic once again.

The watermain disinfection process is nearing completion with water samples now at the lab for bacteriological testing confirmation. Other work remaining to be completed still includes a water service, sidewalk, driveway, and grass restoration. These remaining activities are planned to be completed by the end of next week.