This update covers the last two weeks. Significant progress has been made on Thompson and Walnut with the first course of pavement being placed. Utility work on Wilcox is ongoing.

No work will be performed onsite July 4 or July 5. Enjoy the peace and quiet!

Work Completed The Last Two Weeks

Anticipated Work