This update covers the last two weeks. Significant progress has been made on Thompson and Walnut with the first course of pavement being placed. Utility work on Wilcox is ongoing.
No work will be performed onsite July 4 or July 5. Enjoy the peace and quiet!
Work Completed The Last Two Weeks
- Final grading and placement of the first course of asphalt on Thompson and Walnut.
- Sanitary sewer installation was completed on Wilcox from Edgewater to Walnut.
- Water main installation on Wilcox was completed less final connections.
Anticipated Work
- Connection of the Wilcox water main will be completed at Walnut and Edgewater.
- Water service installation on Wilcox will start the week of July 8. Water service installation on Cherry Street will continue this week.
- Sanitary sewer on Wilcox will be completed from Walnut to the project ending.