Progress Report: Construction of the new sanitary sewer is completed and it is anticipated all adjacent properties will be connected to the new sewer today. Most of the concrete improvements (curb, sidewalk, sidewalk ramps, etc.) scheduled for replacement south of Julia Street have been replaced. Most of the project effort is currently focused within the sanitary sewer reconstruction area. This includes grading the road on the southbound lane of Northland Drive, removing concrete improvements scheduled for replacement, and replacing storm sewer.
Upcoming Work: After all properties are connected to the new sewer the old sewer can be filled with concrete. The contractor will continue to grade the road within the sanitary sewer reconstruction area to prepare for curb and gutter and eventually asphalt paving. Curb and gutter placement within the sanitary sewer reconstruction area is scheduled for Wednesday, June 3. The remaining concrete improvements including driveways, sidewalk, and sidewalk ramp, will be completed after the curb. The contractor will not work Thursday or Friday for the Fourth of July holiday. The site will be cleaned up as much as possible so that everyone can enjoy a long holiday weekend.
Extra Notes: As mentioned above, the curb and gutter will be placed along the west side of Northland Drive from Lewis Street to approximately 800 feet north. This work is scheduled for Wednesday, June 3, weather permitting. Driveways along the west side of Northland drive within this area may be inaccessible until Monday as the curb needs to cure before heavy traffic is allowed. Homeowners and those visiting businesses are encouraged to park on the road during the weekend – the road will be cleared as much as possible to allow room for parking. If you require special accommodations to access your home or business, please contact Dean’s Excavating as soon as possible.