Work Completed This Week

  • Contractor continued placing sanitary sewer mainline on phase II.
  • Contractor continued placing sanitary laterals to homes on phase II.
  • Removed asphalt on phase III (Southern Ave. to Laketon Ave).
  • Performed Removals of curb & gutter, driveways, and sidewalk on phase III.

 

Anticipated Work Next Week

  • Complete placing sanitary lateral stubs on phase II.
  • Complete placing water service stubs on phase II.
  • Begin concrete work at High School.
  • Continue placing storm sewer on phase II.
  • Begin to build road from Strong Ave. towards the South.
  • Begin water services to homes on phase III.