Work Completed This Week
- Contractor continued placing sanitary sewer mainline on phase II.
- Contractor continued placing sanitary laterals to homes on phase II.
- Removed asphalt on phase III (Southern Ave. to Laketon Ave).
- Performed Removals of curb & gutter, driveways, and sidewalk on phase III.
Anticipated Work Next Week
- Complete placing sanitary lateral stubs on phase II.
- Complete placing water service stubs on phase II.
- Begin concrete work at High School.
- Continue placing storm sewer on phase II.
- Begin to build road from Strong Ave. towards the South.
- Begin water services to homes on phase III.